The South River Road Celebration
Please join us on Friday, July 29 at 10 a.m. to celebrate the successful completion of the South River Road Construction Project. It's...
Updated construction schedule for the week of 7/11 and 7/17
Thursday and Friday, July 14 and 15, Continental Paving will have two crews paving side roads and driveways from the Manchester city line...
Revised schedule for week of July 11
A forecast of rain for Sunday has forced the contractor to again reschedule paving operations to Monday night, July 11 from 6 PM-7 AM on...
Schedule for week of June 27
Expect delays at SRR / Meetinghouse Rd intersection Monday morning Crews will start work at 4 a.m. Monday, June 27 at the South River...
Schedule for the week of June 20
The South River Road Project is nearing completion. Beginning Monday, June 20 the final wearing course of asphalt is scheduled to be...
Schedule for the week of June 13
During the next week crews will: Raise drainage structures (catch basins) on South River Road from CVS towards Meeting House Road in...